2006.6 |
proposal submission --> stage-1 approval |
1st PAC |
2007.1 |
stage-2 approval |
2nd PAC |
2009.1 |
completion of the beam-line spectrometer |
|
2009.2 |
first beam to the K1.8BR beam-line |
RUN#22 |
2009.10 |
beam-line commissioning |
RUN#26, 0.040kW, 6.5h |
2009.11 |
beam-line commissioning |
RUN#27, 0.056kW, 14.8h |
2009.12 |
beam-line commissioning |
RUN#28, 0.16-0.55kW, 20.0h |
2010.1-2 |
beam-line commissioning |
RUN#29, 0.32-1.0kW, 50h |
2010.2 |
beam-line commissioning |
RUN#30, 1.0-1.6kW, 55.4h |
2010.4 |
completion of the cylindrical detector system (CDS) |
|
2010.10 |
beam-line commissioning, CDS commissioning |
RUN#35,0.96-3.0kW, 89.5h |
2010.11 |
completion of the 3He-target system |
|
2010.11 |
(E17) SDD commissioning |
RUN#36, 3.0-3.6kW, 29.5h |
2012.2 |
beam-line commissioning for 1.0 GeV/c, CDS commissioning |
RUN#40, 1.2-3.3kW, 148.5h |
2012.4 |
completion of the neutron counter --> ready to run |
|
2012.6-7 |
engineering run |
RUN#43, 3.5-6.0kW, 100.5h |
2012.12 |
engineering run |
RUN#45, 6.5-11kW, 26.7h |
2013.1 |
engineering run |
RUN#46, 15kW, 22.8h |
2013.3 |
1st-production run |
RUN#47, 14.5kW, 51.5h |
2013.4 |
(E31) completion of the D2/H2-target system |
|
2013.4-5 |
calibration run |
RUN#49a, 11-15kW, 16.3h |
2013.5 |
1st-production run |
RUN#49c, 15.5-24kW, 105.1h |
PTEP(2015)061D01, PTEP(2016)051D01 |
2015.4-5 |
calibration run (H2/D2 targets) |
RUN#62, 3-27kW, 160.3h |
2015.10-11 |
commissioning run |
RUN#64, 32/39kW, 12.8h |
2015.11-12 |
2nd-production run |
RUN#65, 39/42kW, 676.7h |
PLB789(2019)620, PRC102(2020)044002, PRC110(2024)014002 |
2016.5 |
(E31) system launch for E31-1st |
RUN#68, 42kW, 6.7h |
2016.6 |
(E31) 1st-production run & (E62/E57) commissioning |
RUN#69(E31)/(E62/E57), 41kW, 207.7h |
2017.4 |
(E31) system launch for E31-2nd |
RUN#74, 42kW, 12.0h |
2018.1-2 |
(E31) 2nd-production run |
RUN#78, 45/50kW, 515.5h |
PLB837(2023)137637 |
2018.6 |
(E62) production run |
RUN#79, 51kW, 431h |
PRL128(2022)112503 |
2019.2-3 |
(E57) commissioning run |
RUN#81, 51kW, 103h |
2019.4 |
(E57) pilot run with H2 |
RUN#82, 51kW, 42h |
2020.6 |
(T77) pilot run with 4He |
RUN#85, 51kW, 74.2h |
PLB845(2023)138128 |
2021.5 |
(E73) phase-I with 3He |
RUN#87, 64kW, 116h |
2023.6 |
(T98) dbar tune |
RUN#90, 50kW, 6.5h |
2024.4-5 |
(E73) phase-II with H2/4He/3He |
RUN#91, 49-82kW, 276h |